Hi Guys,
I prepare a recovery plan from last updated program, i was monitoring the progress based on total Budgeted Cost and all activities were Phisical % type. My project was in delay due to our mistake so i adjust the remaining duration by increasing the productivity and changing some logic. Now i want to use this as a new baseline so which values i have to use. Remaining total Cost or Budgeted total Cost as Planned Value?
I would recommend using as planned value, as if you are mitigating by using additional resources, which I assume is how you have adjusted your productivity, or longer working hours per period etc, your at complete cost will go up, so you need to compensate somehow.
50% of $100 is $50 so 50%, but 50% of your now $120 is not $50 anymore, if that makes sense.