Problem to make Recovery Plan as a new Baseline

Hi Guys,

I prepare a recovery plan from last updated program, i was monitoring the progress based on total Budgeted Cost and all activities were Phisical % type. My project was in delay due to our mistake so i adjust the remaining duration by increasing the productivity and changing some logic. Now i want to use this as a new baseline so which values i have to use. Remaining total Cost or Budgeted total Cost as Planned Value?

R
Robin Clare-Talbot 👤 Member for 15 years 9 months

I would recommend using as planned value, as if you are mitigating by using additional resources, which I assume is how you have adjusted your productivity, or longer working hours per period etc, your at complete cost will go up, so you need to compensate somehow.

50% of $100 is $50 so 50%, but 50% of your now $120 is not $50 anymore, if that makes sense.

N
nadeem Ghulam Qadir 👤 Member for 10 years 7 months

Dear Sir...

Kindly tell me how to calcaulte the planned %  and actual %  and time elapsed of project. with example...

I am waitng  your positive response ..

With Regards

Nadeem

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts