Resource Assignment summary

5 replies [Last post]
Sunil Babu
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Dear All,

After assigning a resource when I open Project - Resource assignment it is showing blank . Is there any settings that has to be changed inorder to show the resource summary ( Budgeted units) by month. Any thing related to report settings to be modified ?

I already added primary resource column and it is displaying that resource.

Awaitig your valuable reply.

Best Regards,

Sunil.

Replies

Zoltan Palffy
User offline. Last seen 7 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

open Project / Resource Assignments 

upper left under layout there is a small upside down triangle click on it 

select filter and make sure that you have the correct filter set

also same place for columns select default 

 

 

 

Sunil Babu
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Zoltan,

Resource usage profile is working fine, problem is that when we open Project / Resource Assignments ..it is not displaying anything. Any Report settings we have to change or not.

Best Regards,

Sunil.

Zoltan Palffy
User offline. Last seen 7 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

if you have assigned a resource to all of your activiites you can select view show on bottom and select resource usage profile

then on the right hand side click resource usage profile options

in the data tab make sure that units is checked  

in the graph tab make sure that calculate average is checked and that Base on hours per time period is checked 

right click the graph area and select timescale and select Year/Month as the time interval 

Sunil Babu
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi Vladimir,

The software is P6 Ver 7.1

Best Regards,

Sunil.

Hi Sunil,

I can answer  to your question explaining where to find all the data on resource assignments in Spider Project. It looks like you mean some other software. Is it present in the discussion forums here? PP has forums on P6, P3, MS Project, Asta, Sciforma, etc. Please specify the software that you use if it is absent in the PP list or put your question in the discussion forum on your software.