P6 Scheduling (F9)

Hi all,

I need help on P6 scheduling. I have a project which starts on Dec. 2015 and after inserting the activities I press F9 and selecting data date which is in Dec. 2015, the activity is registred as having started as I see on the activity information that the start box is checked and the activity bar has changed. My question, why would the F9 (scheduling) make the project to start when the date is a future date?

You comments are appreciated.

A
Arslan Shahid 👤 Member for 11 years

Dear Anthony Obasi,

 

IT IS IMPOSSIBLE THAT PRESSING F9, ADDS ACTUALS TO THE PROJECT.

You must be using " APPLY ACTUALS"

 

You need to play around Calenders to see if it causes any abnormality.

 

Regards,

“For more queries, you can always contact me here or in person:[email protected]

Arslan Shahid

A
Anthony Obasi 👤 Member for 11 years

Thanks Zolton for that reassuring and confident manner in noting pressing F9 will not work this way. I will have to check if soemthing is wrong somewhere.

Thank you.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

pressing F9 would would NEVER make the activity have an actual start date unless you check the actual start box or unless you 

select  “Apply Actuals: from the tools selection.

Forum Sponsor

Top Posters

henrigpc
0 posts
Hashil Ali
0 posts
Nigel Hussey
1 posts
James Williams
74 posts
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts