Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Relationships while Updating

1 reply [Last post]
Raj Kalavar
User offline. Last seen 12 years 15 weeks ago. Offline
Joined: 24 Mar 2011
Posts: 5
Groups: None

I've joined a company as a scheduler and their philosophy doesnt make sense to me. They tell me if the activity is completed, relationships doesnt matter. For example, Activity A is predecessor to Activity B with FS relationship and no lags. They say it is ok for activity B to have start and finish dates ahead of those of Activity A, as long as both activities are completed. They do that all over the schedule and always left the original relationships.

I believe it is wrong to do that even if activities are completed. Can anyone please help me understand why I am right/wrong..

Thanks

 

Raj

Replies

Miklos Hajdu
User offline. Last seen 12 years 2 weeks ago. Offline
Joined: 13 May 2011
Posts: 97
Groups: GPC Malaysia

Raj,

Fact can overwrite plans. If you have two activities A (10 days), and B (10 days), and a FS0 from A to B, and on day 10 you go to the site and experience that A has started but not finished yet (you need two more days), but B has started two days ago, then this is the fact that overwrite the plan.

It means that your original FS0 was wrong somehow, because you could start B before the finish of A. So relation doesn't count in this case.

However if you did not start B, then you should estimate its start after the expected finish of A. So relations count in this case.

Hope I could help you

Miklós.