Relationships while Updating

Member for

14 years 5 months

Raj,

Fact can overwrite plans. If you have two activities A (10 days), and B (10 days), and a FS0 from A to B, and on day 10 you go to the site and experience that A has started but not finished yet (you need two more days), but B has started two days ago, then this is the fact that overwrite the plan.

It means that your original FS0 was wrong somehow, because you could start B before the finish of A. So relation doesn't count in this case.

However if you did not start B, then you should estimate its start after the expected finish of A. So relations count in this case.

Hope I could help you

Miklós.