Progress Percentage by using late dates

Dear Friends 

Suppose you have an activity A .

whose early dates are 

Early Start  1 Apr 11 

Early Finish  30 Apr11

Whose Late Dates area 

Late Start 25 April 11

Late Finish 10 May 11

Now we are at 1 may , as per ealry dates your  planned progress must be 100 % while the  activity is 90% complete. This shows that it is delayed , now we want to use float then how to calculate planned progress  ?  so as not to show that we are delayed 

Thankyou 

Umer Mehmood

 

G
Gary Whitehead 👤 Member for 17 years 3 months

Typically you would plot 3 progress curves: planned (early), planned (late) and actual/forecast.

This is often called a "banana graph"

Forum Sponsor

Top Posters

Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts
Dave Morgan
0 posts
blake333_
0 posts
Mohammed Netarwala
12 posts
Moahmed
0 posts