Default Curve To All Resources

1 reply [Last post]
Shahid Chauhdary
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 26 May 2008
Posts: 4
Groups: None

Can we assign / change the default curve on all the resources that are assigned on activities?

Like i want to assign a TRAPEZOIDAL curve to all the resources on all the activities.

Replies

MAYUKH DATTA
User offline. Last seen 11 years 22 weeks ago. Offline
Joined: 4 Sep 2003
Posts: 7

Shahid,

Yes it is possible in P6, but in an indirect way....

1) You need to define your curve profile first in P6 and give a name.

2) Export all the activities into excel with "Curve" as a resource assignment field.

3) Fill the curve profile name in the "curve" profile column in the excel sheet

4) Import the same file to P6.

 

This is the indirect way of assigning resource profile to activities in a bulk, else you have to go to the activities one by one and change the resource profile. I understand that any direct method of assigning resource profle to bulk activities in Primavera is still not available.

 

Hope this answers your query.