Procurement period of pipes

4 replies [Last post]
kier legard
User offline. Last seen 14 years 40 weeks ago. Offline
Joined: 31 Jul 2006
Posts: 96
Groups: None

Hi to All,


Does anybody know of the procurement of the following pipes.

DUCTILE IRON
a. pipes
b. fittings
c.valves

GRP
a. pipes
b. fittings

Pvc
a. pipes
b. fittings

HDPE
a. pipes
b. fittings
c.valves

CARBON STEEL

a. pipes
b. fittings
c.valves

I would appreciate if somebody can help me.

Best Regards,

kier

Replies

Glenn Douglas
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 22 Apr 2006
Posts: 39
I have been trying to get CS tube and the lead time varies from country to country.
Sometimes the client insists that tube or pipe has to be of european or Nth American origin which can be a lead time of 35 weeks (especially if its seamless & not welded). Whilst I have been getting better lead times from China and Estonia.
Our procurement dept are now trying every corner of the globe.
A D
User offline. Last seen 3 years 46 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
It depends upon your supplier exclusively. His factory profuction capacity, stock at that period and projects in his hand.

So, its better to call ur vendor rather than asking from planners.

Se de Leon
User offline. Last seen 3 years 8 weeks ago. Offline
Joined: 15 May 2001
Posts: 321
Groups: None
Call your vendors for more accurate answer. Don’t rely on planners, because planners do also ask suppliers for this kind of information.
Nar Thap
User offline. Last seen 16 years 22 weeks ago. Offline
Joined: 12 Sep 2007
Posts: 73
My poject is using CS pipes 20" dia. or more, and fittings previosuly estimate 33 wks of lead in time but the vendour is quite quick getting it ready in 20 wks.