Planning in Pakistan

5 replies [Last post]
Jason Frost
User offline. Last seen 19 years 7 weeks ago. Offline
Joined: 29 Aug 2005
Posts: 4
Groups: None
I am looking currently looking at a project in Pakistan and have no idea as to the skill/expertise of the contractors in this country.

The project consists of several 35+ storey buildings of mixed use sitting on a podium car park.

Could anyone advise me on

1) The contracors within Pakistan with the expertise to complete this project

2) The type of construction generally used for high rise ie Steel, Concrete or hybrid

3) Typical cycle time per floor

Jason

Replies

Shahab Ali
User offline. Last seen 13 years 6 weeks ago. Offline
Joined: 19 Apr 2004
Posts: 24
Top listed contractors in pakistan

1)Descon Engineering limited
2)Habib Rafique
3)SKB
4)Sachel
5)Chinese............compnies i.e on mangla etc
6)Italian...........compies...i.e impregilio...

If u need some, u can ask me..

regards,

Shahab
Kashif Hussain Fa...
User offline. Last seen 11 years 44 weeks ago. Offline
Joined: 25 Jan 2004
Posts: 4
I am working in Karachi, Pakistan as a planning engineer for multi-story building project having 12 buildings each ground + 17 floors. The project is being awarded to top contractors of the country :
1. Associated Constructors Pvt. Ltd
2. Habib Rafiq Pvt. Ltd.
3. Builders Associates Pvt. LTd.

The floor cycle we have achieved so far, varies from 15 days to 22 days depending on the formwork system. Completion period of one floor is about 26 days. Structure work is in progress.

If you need any more information, please don’t hesitate to send e-mail to kashifstudy@yaoo.com

Thanks,
Kashif Farooqui
Planning Engineer
Zhang Haixiang
User offline. Last seen 4 years 6 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
i have no idea of this kind of buiding.
I think you can find good contractor there.
We have built a nuclear powerplant there, most of the civil works are done by local contractor.
Jason Frost
User offline. Last seen 19 years 7 weeks ago. Offline
Joined: 29 Aug 2005
Posts: 4
Groups: None
Thanks Shahzad,

Unfortunately it is not that job in Islamabad but rather Karachi.

Jason
Shahzad Munawar
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
I think you are coming from Al Habtoor Group for their project in Islamabad.

There are different contractors in Pakistan who have ability to complete such type of structures but limited to 15~25 stories at best.

Completion period for one Floor is from 20~30 days.