VBA Excel for Primavera Gantt Chart

Hello everyone,

I'm wondering if anyone has VBA code or any other type of written code that allows you to generate an Excel Gantt chart and all related elements with a single button click from Primavera?

A
Alex Lyaschenko 👤 Member for 14 years 10 months

Abbas, 

It depend what do you mean under "generate Gantt Chart". Is it to draw Gantt in Excel based on Primavera data, no VBA is required for that.

This can be accomplished using straightforward Excel formulas and a basic understanding of Excel. Experienced planners have their own version of "Gantt in Excel" tool, which they can develop in just a few hours.

 

Regards,

Alex Lyaschenko