Longest path in under specific WBS

R
rauf kensuk 👤 Member for 6 years 5 months

Hi All, I am working with 20 different construction under one P6 Program. Example WBS as below;  

 1. Facility Construction

1.1. Block A

1.2. Block B

1.3. Block C and goes on. they are not connected to each other. their only intersection is project start finish activity   

I am trying to find the longest path for specific Block. what I mean is filtering longest Path in "Block A".   

When I "Longest Path" filter in P6, it runs for all WBS. What should I do for Longest Path in specific WBS or Block ?  

D
david kelly 👤 Member for 10 years 4 months

Rauf,

 

Each of the 20 buildings should be a separate project. Of course, you need a Global Activity code instead of/as well as the project specific WBS which is such a dissapointment in an 'Enterprise' environment.

The scheduling options allows selecting one float path per portfolio, or one float path per project with a single tick box.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

filter

ALL

where wbs equals Block A

and 

where longest path equals yes

D
david kelly 👤 Member for 10 years 4 months

Rauf,

 

Each of the 20 buildings should be a separate project. Of course, you need a Global Activity code instead of/as well as the project specific WBS which is such a dissapointment in an 'Enterprise' environment.

The scheduling options allows selecting one float path per portfolio, or one float path per project with a single tick box.

R
Rodel Marasigan 👤 Member for 19 years 8 months

You can use float path filter. 

To calculate float path:

1) Press F9 (run schedule) then click Options

2) Select Advance Tab then tick calculate multiple float paths

3) Tick Free Float then on Display multiple float paths ending on activity click ... on right side of text box and select the last activity of WBS (say Block A) that wanted to calculate longest path.

4) On Specify the number of float paths to calculate -> change the number to 1

5) Then click Close and click Schedule

6) After running the schedule, create a filter and name it with Float Path (recommended name) Where Float Path equal 1 (criteria)

7) Apply the filter and it will show the longest path of selected WBS

Do the same to other WBS

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts