Hello everyone, I am facing a problem in resource leveling. After completion the scheduling, I faced with overallocation. As a result, i defined priority and used leveling, but unfortunately no change is happened. anybody has idea what could be the reason? Thanks
Resource Leveling
Forum Sponsor
Top Posters
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
Rodel,
Rodel,
Hamid,
Make sure that no overallocated on each activities as it will not move because it is already overallocated. Overlaping activities is fine as long as it will be level accordingly. Make sure the maximum limit is set ex: say 5 res x 8hrs/day = 40hrs/day
Hi Hamid,
As you mentioned, your setting is Fixed Units. Is the activity itself is over allocated? It so then overallocated resource on activities will not move or will not level.
Hi Rodel,
I selected “Preserve scheduled early and late dates” and some change has happened, but still, I am faced with over-allocated resources in some parts.
Hi Rodel,
I selected “Preserve scheduled early and late dates” and some change has happened, but still, I am faced with over-allocated resources in some parts.
Hi Hamid,
When you run Level Resource (shift+F9). Did you select:
1. Automatically Level Resources when scheduling
2. Preserve schedule early and late dates
3. Level all resources
Also did you select the field names you use for levelling priorities?