Color Activity not meeting Baseline

Hello Everyone,

 

Is there a way by which the Activity Bar which didnt meet the Basline Date can be highlighted in a different colour Say like Orange.

 

Red coloured bar is critical activity, but I would like to show activities which hasnt met the baseline date in Yellow.

 

Any chance ?

 

Thanks

Jithin

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hi Jithin,

you can create a new bar in wich you will assign a filter based on the "Variance BL1 Start Date", or "Variance BL1 Finish Date", or both

Alexandre