P6 Error: TDBXError - VTRAT-4016-2 - TCVirtualTable.RefreshAppend: TASKRSRC: database disk image is malformed

M
Manh Hoang 👤 Member for 6 years 8 months

Hello Gents/Madams,

I am using P6 Professional 18. When I imported a MS Project (XML), it was unlucky that It got an error like that:

Type: TDBXError

Event Code: VTRAT-4016-2

Description: TCVirtualTable.RefreshAppend: TASKRSRC: database disk image is malformed

So, I cannot open any projects (poor me)…

Do you have any solutions for this issue?

Thank you and with warm regards!

ManhHoang

Z
Zoltan Palffy 👤 Member for 16 years 11 months

I can give you step by step instruction if you give me your email address

M
Manh Hoang 👤 Member for 6 years 8 months

Yes, I am using P6 Standardalone.

Do anyone have any right ways to solve this issue?

all my project is still in the database.... hic

Z
Zoltan Palffy 👤 Member for 16 years 11 months

are you usig  P6 Standalone, with an SQLite database ?

The SQLite database has become corrupted or damaged.

it wil lhave to be rebuilt 

Forum Sponsor

Top Posters

Lee Mallek
23 posts
Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts