Remove float for all in progress activities

N
Narsis Kas 👤 Member for 7 years 3 months

Hi

Is there a quick way to remove float and make all activities critical? Client wants to know what happen to the project finish date if remove the float

Thanks

Z
Zoltan Palffy 👤 Member for 16 years 11 months

then insert a 9 month activity into the current critical path of the schedule 

S
Santosh Bhat 👤 Member for 21 years 2 months

All activities being critical, is the same as no activities being critical.

N
Narsis Kas 👤 Member for 7 years 3 months

Thanks Both Santosh and Zoltan, I agree with you both. I'm awar making all activities critical is not correct. This request actually is becouse of 9 months delay in the project and client wants to know if all activities get critical what will happen to the project finish date.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

the only way that there is no float is when the activity is finished. You can't remove float you can adjust is value by increasing or reducing durations, changing logic or by adding constrcint dates.

total float is a calculation between the early dates and the late dates plain and simple. 

S
Santosh Bhat 👤 Member for 21 years 2 months

You dont "remove" float. Float is a output of the critical path method scheduling calculation.

 

If you're gaming your schedule to show a sequence of tasks as critical, then look at the total float value of a task, and increase its duration by the total float amount, and then it and all subsequent tasks should appear as critical.

But I would suggest a more thorough review of the schedule to understand why you want to do the above.

Forum Sponsor

Top Posters

GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts