Monthly Planned progress from P6 without Cost/Resource

2 replies [Last post]
yahya kutarvadali...
User offline. Last seen 23 weeks 6 days ago. Offline
Joined: 2 May 2015
Posts: 3

Dear All

i am working on epc project, our time schedule is not cost & resource loaded means only time schedule.

is there any ways/methods to determine monthly plan % ??

Replies

Zoltan Palffy
User offline. Last seen 21 weeks 16 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

although I do not recommend this technique you can do it 2 ways

1 way is strictly tiime based and the other way is to calculate when actiivities were planned to FINISH vs when or is they have finished

send me your email address and I will show u how to do this 

you can also use project tracker you can get a free trial here

https://www.willmer.co.uk/

David Kelly
User offline. Last seen 2 years 2 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Since you do not have any costs or resources, the monthly planned per cent complete is one month.