Which Primavera P6 Percent Complete Type to Use?

2 replies [Last post]
Emily Foster
User offline. Last seen 2 years 11 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

Primavera P6 has three different ways to track schedule progress. Here we explore the best applications for each type  http://ow.ly/Mxpq302V5DS

Replies

Emily Foster
User offline. Last seen 2 years 11 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

Hi David - Love it!

David Kelly
User offline. Last seen 2 years 2 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Simple:

 

If you are an Owner who employs contractors,  you use Duration

If you are one of those contractors, you use Physical (the only way to keep Earned Value, Remaining Duration, and Remaining units independent)

If you are the victim of a cruel medical experiment, you use Units