Hiding unwanted nodes in Project Portfolio

D
David Ball 👤 Member for 18 years 10 months

Hi All,

I have set up a Project Portfolio containing three projects. The problem is all the other nodes are still showing, making it difficult to find my projects.

How can I set it up so that only my three projects are displayed?

 

Thanks very much

 

Dave

D
David Ball 👤 Member for 18 years 10 months

Yes, I select, File, Open, then my Portfolio. But it shows my three projects and all the nodes/bands of every other project as well.

 

I was expecting that it would just the three projects from my portfolio and nothing else

Z
Zoltan Palffy 👤 Member for 16 years 11 months

you can only filter for one portfolio at a time so it will so show up in each portfolio that you select sepeately

I do not know what you are trinng to do but you can also assign a project status to a project then filter for the staus of the projects

Z
Zoltan Palffy 👤 Member for 16 years 11 months

so I assume that you have assigned one or more project to a portfolio that was there or a new portfolio that you have created.

So you have assigned the project to the portfoilio of your choice

THe trick to seeing only the projects in the portfolio is to select file then open  

then at the top in the drop down instead of all project select your portfolio and only the projects that you hjave assigned to the portfolio will be displayed.

think of it as another way to filter but at the project level based on portfolios

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts