custom page break when converting to PDF

Hi

 

I was wondering if it was possible to insert a page break before converting to PDF.

Currently my schedule runs over 4 A3 pages but the pages are split in the middle of the WBS.

in one case the Heading of one WBS is at the bottom of the page with the first task appearing at the top of the next page.

Is it possible to set a custom page break on the scheudle or print before converting to PDF.

 

Any help very much appreciated.

 

Regards

 

Eoin

Z
Zoltan Palffy 👤 Member for 16 years 11 months

look under view group and sort 

grouping is used to group and organize your activities 

also known as banding 

R
Raymund de Laza 👤 Member for 16 years 6 months

In relation to Zoltan suggestion do the FF:

1. Create Activity Codes Similar to your WBS.

2. Assign the Activites accordingly.

3. Use the Group and Sort and organized according to the New Created Act Codes.

4. In the Page Setup .. Options Check the Checkbox Break Page Every Group

 

Hope this will help

E
Eoin Flannery 👤 Member for 10 years 10 months

thanks for the reply but could you expand on what you mean when you say grouping?

 

Where is this option and i will take a look.

 

the row height is just pianful and too much trial and error.

 

you would think its a pretty simple thing to implement. like say in excel where you can simply drag a blue line.

 

PS (not for a second comparing excel to P6 just trying to make a simple point!!!)

Z
Zoltan Palffy 👤 Member for 16 years 11 months

if you group by a code or the wbs but do not indent than you can go to print preview 

then page setup

then options

then at the bottom check page break on group

other than that you would have to play wiht the row height to get what you want to do. 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts