Oracle Primavera - PM6 Member for 9 years 10 months Member for 9 years 10 months Submitted by LOKESHBABU_K on Tue, 2016-10-18 09:10 Permalink Hello Kindly help me on the Hello Kindly help me on the error com.primavera.integration.client.ClientException: Fatal error: null at com.primavera.integration.client.Session.a(Session.java:379) at com.primavera.integration.client.Session.login(Session.java:339) at com.primavera.integration.app.importexport.ImportExportAction.b(ImportExportAction.java:172) at com.primavera.integration.app.importexport.ImportExportMain.main(ImportExportMain.java:33) Original Exception: java.lang.NullPointerException at com.primavera.bo.datacaches.ServerUserPrivsCache.getServerUserPrivsCache(ServerUserPrivsCache.java:765) at com.primavera.bo.common.b.a(LoginHelper.java:360) at com.primavera.bo.common.b.a(LoginHelper.java:166) at com.primavera.bo.remotable.SessionLifetime.login(SessionLifetime.java:57) at com.primavera.bo.remotable.qproxy.SessionLifetime.login(SessionLifetime.java:76) at com.primavera.bo.DBSessionLifetime.login(DBSessionLifetime.java:26) at com.primavera.integration.server.ServerFacadeBase.login(ServerFacadeBase.java:411) at com.primavera.integration.server.ServerFacade.login(ServerFacade.java:11) at com.primavera.integration.client.LocalSession.login(LocalSession.java:92) at sun.reflect.NativeMethodAccessorImpl.invoke0(Native Method) at sun.reflect.NativeMethodAccessorImpl.invoke(Unknown Source) at sun.reflect.DelegatingMethodAccessorImpl.invoke(Unknown Source) at java.lang.reflect.Method.invoke(Unknown Source) at com.primavera.integration.client.Session.a(Session.java:351) at com.primavera.integration.client.Session.login(Session.java:339) at com.primavera.integration.app.importexport.ImportExportAction.b(ImportExportAction.java:172) at com.primavera.integration.app.importexport.ImportExportMain.main(ImportExportMain.java:33) Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2015-02-10 12:48 Permalink glad I could help glad I could help Member for 10 years 9 months Member for 10 years 9 months Submitted by Reece1984 on Wed, 2015-01-28 22:05 Permalink It worked! Thank you very It worked! Thank you very much Zoltan! Member for 10 years 9 months Member for 10 years 9 months Submitted by Reece1984 on Wed, 2015-01-28 22:05 Permalink It worked! Thank you very It worked! Thank you very much Zoltan! Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2015-01-26 18:35 Permalink This issue is caused by using This issue is caused by using an unsupported Java JRE version (1.8.x) To solve this issue 1) Uninstall the actual Java 1.8.0_X from the machine. 2) Install a Java version that appear in the tested configuration list for your P6 version Primavera Official Documentation > Select your P6 version > click on "Tested Configurations" > select the tab Client. 3) Configure the JAVA_HOME to point to this new java environment following 4) Reboot machine. Log in or register to post comments
Member for 9 years 10 months Member for 9 years 10 months Submitted by LOKESHBABU_K on Tue, 2016-10-18 09:10 Permalink Hello Kindly help me on the Hello Kindly help me on the error com.primavera.integration.client.ClientException: Fatal error: null at com.primavera.integration.client.Session.a(Session.java:379) at com.primavera.integration.client.Session.login(Session.java:339) at com.primavera.integration.app.importexport.ImportExportAction.b(ImportExportAction.java:172) at com.primavera.integration.app.importexport.ImportExportMain.main(ImportExportMain.java:33) Original Exception: java.lang.NullPointerException at com.primavera.bo.datacaches.ServerUserPrivsCache.getServerUserPrivsCache(ServerUserPrivsCache.java:765) at com.primavera.bo.common.b.a(LoginHelper.java:360) at com.primavera.bo.common.b.a(LoginHelper.java:166) at com.primavera.bo.remotable.SessionLifetime.login(SessionLifetime.java:57) at com.primavera.bo.remotable.qproxy.SessionLifetime.login(SessionLifetime.java:76) at com.primavera.bo.DBSessionLifetime.login(DBSessionLifetime.java:26) at com.primavera.integration.server.ServerFacadeBase.login(ServerFacadeBase.java:411) at com.primavera.integration.server.ServerFacade.login(ServerFacade.java:11) at com.primavera.integration.client.LocalSession.login(LocalSession.java:92) at sun.reflect.NativeMethodAccessorImpl.invoke0(Native Method) at sun.reflect.NativeMethodAccessorImpl.invoke(Unknown Source) at sun.reflect.DelegatingMethodAccessorImpl.invoke(Unknown Source) at java.lang.reflect.Method.invoke(Unknown Source) at com.primavera.integration.client.Session.a(Session.java:351) at com.primavera.integration.client.Session.login(Session.java:339) at com.primavera.integration.app.importexport.ImportExportAction.b(ImportExportAction.java:172) at com.primavera.integration.app.importexport.ImportExportMain.main(ImportExportMain.java:33)
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2015-02-10 12:48 Permalink glad I could help glad I could help
Member for 10 years 9 months Member for 10 years 9 months Submitted by Reece1984 on Wed, 2015-01-28 22:05 Permalink It worked! Thank you very It worked! Thank you very much Zoltan!
Member for 10 years 9 months Member for 10 years 9 months Submitted by Reece1984 on Wed, 2015-01-28 22:05 Permalink It worked! Thank you very It worked! Thank you very much Zoltan!
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2015-01-26 18:35 Permalink This issue is caused by using This issue is caused by using an unsupported Java JRE version (1.8.x) To solve this issue 1) Uninstall the actual Java 1.8.0_X from the machine. 2) Install a Java version that appear in the tested configuration list for your P6 version Primavera Official Documentation > Select your P6 version > click on "Tested Configurations" > select the tab Client. 3) Configure the JAVA_HOME to point to this new java environment following 4) Reboot machine.
Member for
9 years 10 monthsHello Kindly help me on the
Hello Kindly help me on the error
com.primavera.integration.client.ClientException: Fatal error: null
at com.primavera.integration.client.Session.a(Session.java:379)
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
10 years 9 monthsIt worked! Thank you very
It worked! Thank you very much Zoltan!
Member for
10 years 9 monthsIt worked! Thank you very
It worked! Thank you very much Zoltan!
Member for
16 years 3 monthsThis issue is caused by using
This issue is caused by using an unsupported Java JRE version (1.8.x)
To solve this issue
1) Uninstall the actual Java 1.8.0_X from the machine.
2) Install a Java version that appear in the tested configuration list for your P6 version Primavera Official Documentation >
Select your P6 version > click on "Tested Configurations" > select the tab Client.
3) Configure the JAVA_HOME to point to this new java environment following
4) Reboot machine.