Tracking of Predecessors for change of Remaining Early Start date

Dear Planners

 

If one of predecessors is not completed (out of sequence progress) using retained logic, start of successor activity is delayed until all of predecessors are completed. (Remaining early start date is delayed)

It is required to track what activities are not completed. In case of complex project with thousands of activties and lots of relationships, it is very difficult to find which predecessors are not completed.

Is there any solution to find un-completed activities in predecessors easily ?

Simple Filtering of activities are not useful becasue there are so many activities, I just want to filter certain activities linked.

Thank you in advance

Z
Zoltan Palffy 👤 Member for 16 years 11 months

if you filter for longest path AND critical path you shoudl be able to get waht you are looking for 

also when you schedule check the log file this wil tell you where you have out of sequence progress

Forum Sponsor

Top Posters

bal aji
2 posts
Lee Mallek
23 posts
Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts