Hi I am a new member and really need help! Could anyone tell me how to split or a Suspend a activity but still carry out work on sucesscessor activity at same time how to show this on a gantt. Thankyou in advance Rammy
Splitting Activity in P6
Forum Sponsor
Top Posters
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
Activities are usually already split on a day by day basis on most schedules. The split already happens on non-work hours and days such as week-ends, holidays etc. All you have to do is add non-work calendar exceptions to you activity calendar, preferably an individual calendar as not to impact other activities you do not want to.
Then by necking you will be able to see when activity will split after DD, either an ongoing or a future split.
Depending on software you might not be able to see splits on past performance bars but with use of histograms you will.
This method does not add new activities, will keep all logic, costs etc valid.
For permanently suspended activity use appropriate RD or actual finish date and adjust remaining duration and cost data as required.
For temporary suspension with unknown resume date on every update add required non-work days up to update DD.
You can suspend only a started activity and there is no issue in carrying out works on a succeeding activity in such a case. However, you will need to be very careful about the results you get thus. I guess it will need to be analyzed on a case to case basis and can't be generalized.
Hi Rammy
Break the successor link and link around the suspended task.
re Link when required.
In Asta Powerproject you can give the suspended link a category name and de activate it.
Best regards
Mike Testro