Oracle Primavera - PM6 Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Wed, 2014-04-23 16:07 Permalink Asta and Spider both have Asta and Spider both have this facility. Member for 17 years Member for 17 years Submitted by Haroon Rasheed on Wed, 2014-04-23 13:56 Permalink Hello Gary,Thanks for the Hello Gary, Thanks for the response. Are you aware of any other software that can do it? Haroon Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Mon, 2014-04-21 17:34 Permalink Nope. One of Primavera's Nope. One of Primavera's major failings, this. The best you can do is SS+lag, with the lag representing the estimated time required to achieve the desired % complete. Other alternative is to split the predecesor activity into 2, and use FS links Log in or register to post comments
Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Wed, 2014-04-23 16:07 Permalink Asta and Spider both have Asta and Spider both have this facility.
Member for 17 years Member for 17 years Submitted by Haroon Rasheed on Wed, 2014-04-23 13:56 Permalink Hello Gary,Thanks for the Hello Gary, Thanks for the response. Are you aware of any other software that can do it? Haroon
Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Mon, 2014-04-21 17:34 Permalink Nope. One of Primavera's Nope. One of Primavera's major failings, this. The best you can do is SS+lag, with the lag representing the estimated time required to achieve the desired % complete. Other alternative is to split the predecesor activity into 2, and use FS links
Member for
16 years 7 monthsAsta and Spider both have
Asta and Spider both have this facility.
Member for
17 yearsHello Gary,Thanks for the
Hello Gary,
Thanks for the response.
Are you aware of any other software that can do it?
Haroon
Member for
16 years 7 monthsNope. One of Primavera's
Nope.
One of Primavera's major failings, this.
The best you can do is SS+lag, with the lag representing the estimated time required to achieve the desired % complete.
Other alternative is to split the predecesor activity into 2, and use FS links