Linking activities based on physical % complete

3 replies [Last post]
Haroon Rasheed
User offline. Last seen 9 years 21 weeks ago. Offline
Joined: 14 Oct 2008
Posts: 19
Groups: None

Hello evereyone,

Is there any method by which one can link an activity based on the predecessor's physical % complete in Primavera P6?

Linking SS or FS - is not serving the purpose.

Thanks in advance.

Haroon

Replies

Gary Whitehead
User offline. Last seen 5 years 10 weeks ago. Offline

Asta and Spider both have this facility.

Haroon Rasheed
User offline. Last seen 9 years 21 weeks ago. Offline
Joined: 14 Oct 2008
Posts: 19
Groups: None

Hello Gary,

Thanks for the response.

Are you aware of any other software that can do it?

 

Haroon

Gary Whitehead
User offline. Last seen 5 years 10 weeks ago. Offline

Nope.

 

One of Primavera's major failings, this.

 

The best you can do is SS+lag, with the lag representing the estimated time required to achieve the desired % complete.

 

Other alternative is to split the predecesor activity into 2, and use FS links