Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Generate S-curve in P6 R8.2

3 replies [Last post]
Leonard Esber
User offline. Last seen 9 years 31 weeks ago. Offline
Joined: 19 Jul 2013
Posts: 16
Groups: None

Dear colleagues,

Just want to know, in P6 R8.2, how to generate s-curves for the following:

     1. Cost (Plan vs. Actual)

     2. Earned Value

     3. Schedule Variance

     4. Resource Loading

Regards,

Leonard

Replies

Adolfo Caccialanza
User offline. Last seen 5 years 25 weeks ago. Offline
Joined: 3 Oct 2009
Posts: 14
Groups: None

The best solution for Progress Curves Early & late is at this site:

 

http://www.cla-it.eu/TMSDetails-general.html

 

Best regards

Chris Rymer
User offline. Last seen 3 years 9 weeks ago. Offline
Joined: 11 Jun 2010
Posts: 32
Groups: None
Have a look at Project Tracker, the new software that generates S curves directly from P6. There is no need to export the data to a spreadsheet, Project Tracker will do it all for you. S curves can be created from the duration of the activity as well as resource and cost allocations. More information can be found at www.willmer.co.uk
Adam Garnham
User offline. Last seen 9 years 38 weeks ago. Offline
Joined: 3 Oct 2011
Posts: 23
Groups: None

Hi Leonard

Might need some more info here mate - what exacting are you looking for? How to view the current spend profiles as curves or how to profile spend as an S-curve?

To view the current spend profiles of your schedule go to the Resource Usage Profile screen, right clicking on the graph area will allow you to select Timescale and Resource Usage Profile Options to tailor the graph. This will display the current profiles.

To assign Curves to resource loaded activities you will need to select the relevant activity, open the Resources tab of the Activity Details window, and right-click add the Curve column to the table. Then you can select from pre-defined curves by double clicking in the newly added column. If none of the curves fit then you can create your own. But I will wait see if this helps you first.

Regards

Adam