Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Displaying Two Calendars Non-Work Time on Gantt Chart

3 replies [Last post]
Tony McClennon
User offline. Last seen 42 weeks 6 days ago. Offline
Joined: 19 Nov 2002
Posts: 97
Groups: None

Hi,

I suspect already that the answer is no, but just in case here goes.......!!

I have a couple of tasks that are planned to be undertaken over a weekend. I have a separate calendar set up for weekend working only, and MSP schedules the tasks correctly on the Saturday and Sunday.

I have the "Standard" Monday to Friday Calendar set up to show the non-working times, which is then displayed in front of the tasks, correctly showing that the majority are not working over weekends.

This does mean though that the tasks that are weekend working are hidden behind the shading - is there any way that I can format the Gantt chart to show these weekend tasks in front of the shading, or at least hide the shading for these particular tasks?

Many thanks.

Replies

Se de Leon
User offline. Last seen 3 years 16 weeks ago. Offline
Joined: 15 May 2001
Posts: 321
Groups: None

You can change the format option for non work times from draw in front of task bars into draw behind task bars.  I hope this helps.

Tony McClennon
User offline. Last seen 42 weeks 6 days ago. Offline
Joined: 19 Nov 2002
Posts: 97
Groups: None

As I suspected Tom, but thanks for confirming this - just needed to check I hadn't missed a workaround!!!

Tom Boyle
User offline. Last seen 11 weeks 3 days ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

Sorry Tony,

I think you are stuck.  About the best you can do is put the non-working time behind the bars.

Good luck, tom