Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Can not select task type

3 replies [Last post]
Ahmet Tuter
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 7 Feb 2013
Posts: 52
Groups: None

I just started a new project and i entered two activities so far.

I want to select task type.

i am at task information > advanced tab, and i see the options there but they are disabled.

I can not select task type . Effort driven checkbox is also disabled

Replies

David Manna
User offline. Last seen 6 years 45 weeks ago. Offline
Joined: 26 Nov 2017
Posts: 13
Groups: None

I am learning MS project and very excited to use it for our new project. I was having the same issue. Thanks for the solution guys.  

Ahmet Tuter
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 7 Feb 2013
Posts: 52
Groups: None

thanks you are right. they were manually scheduled and i turned it off

Tom Boyle
User offline. Last seen 11 weeks 6 hours ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

These options are disabled for summary tasks and for manually scheduled tasks.  I would suspect yours is manually scheduled.