Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Calenders

3 replies [Last post]
Dan Mårtensson
User offline. Last seen 10 years 22 weeks ago. Offline
Joined: 23 Jun 2014
Posts: 4
Groups: None

Hi all,

 

I´m sitting on a concern that I hope you can help me with.

 

I have diffrent work packages that need diffrent calenders. I creat the calenders of the various jobs that exist.

What happens is that if I plan more then 8 hours a day so shortened duration down and make my activity shorter. I want to add 10 days, but the pace of work at 12 hours a day.

 

How can I do this?

 

Greatful for a quick reply

 

Regards

 

Dan

Replies

Dan Mårtensson
User offline. Last seen 10 years 22 weeks ago. Offline
Joined: 23 Jun 2014
Posts: 4
Groups: None

Thank you!

 

The problem got slowed yesterday

 

/Dan

Evgeny Z.
User offline. Last seen 1 year 18 weeks ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

Dan,

you need to create a seporate calendar and assign it to this spesific task:

See the link below:

http://office.microsoft.com/en-gb/project-help/set-working-times-vacatio...

Consider also Task option "Scheduling ignors resource calendar"

Regards.

Dan Mårtensson
User offline. Last seen 10 years 22 weeks ago. Offline
Joined: 23 Jun 2014
Posts: 4
Groups: None

Anyone?

 

/Dan