Project Overview
Forum Sponsor
Top Posters
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
MSP variance is ok.
we can use formula to calculate variance to our requirements(whatever may be the baseline).
Gary & Samer,
it is not possible in MS Project to select a specific baseline as the "default baseline" against which MSP would compare "Actual" to calculate a Variance.
Project overviews Variance is always calculated between Actual Start / Finish and Baseline Start / Finish; where "Baseline" stands for "Initial Baseline" with no number (i.e. <> "Baseline1", ...
if you want to save a 2nd baseline and have it used in the Variance, you will have to save "Baseline" as "Baseline1" first, then save the current project as "Initial Baseline (no number)" again
Alexandre
Dear Gary,
The variance is between any two schedules that you select.
With kind regards,
Samer