MSP Baslines
Forum Sponsor
Top Posters
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
Andrew
Make sure the activities are logic linked correctly, that you have no constraints, you have a critical path identified wthin the project etc.
When updating a project you must save the baseline firstly ( Save Baseline ).
Go into Tracking Gantt.
Insert Columns .... Activity Name / Baseline start / baseline finish / Actual Start / Actual Finish Per complete
Go to Tools > Tracking > Progress Lines > Input the data / progress line date.
Input the ACTUAL Start and Finish Dates against each activity. If some activities have started but are incomplete then you must put in a percentage.
The project is now being progressed.
Hello Alexandre ,
Yes I am posting the progress in the tracking option.
Andrew
Andrew,
are you entering the progress in the tracking table fields?
Alexandre