Assign Resources

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Pacifico,

it is possible to assigne resources the way you want, but I would suggest you don’t and create two activities instead

I assume that the 2 or 3 carpenters are working full time

1. set the activity type as Fixed Duration (Activity Info, Advanced, Activity Type)

2. Display the Task Usage View

3. Assign TWO carpenters to the task

4. browse the task in the right pane of the screen until you reach day 6

5. change the amount of work from 14h (or 2d) to 21h (or 3d)

6. do the same until day 10.

That’s all, hombre

Alexandre

Forum Sponsor

Top Posters

Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts