Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Assign Resources

1 reply [Last post]
Pacifico Pallasigui
User offline. Last seen 12 years 11 weeks ago. Offline
Joined: 24 Jan 2004
Posts: 62
Groups: None
Can anybody help how to assign resources in 1 activity

Duration: 10 days
First 5 days of the duration = 2 carpenter
other 5 days of the duration = 3 carpenter

is this possible to MS project or ill break the activity?

Replies