Sukumaran - many thanks, just the thing.I must have been having one of those "forgetful" moments!!!
Regards,
Tony
Go to Tools > Options > Schedule and in the following field "DURATIONS IS ENTERED IN" change to either Weeks or Months.
Regards.
Sorry - should have mentioned that I am working with MSP2000.
Tony