If the contract form is a JCT Private with Approximate Quantities : 1986 then in accordance with clause 13 it states "The quality and quantity of the works included in the Tender Price shall be deemed to be that which is set out in the Contract Bills".
I have not researched later editions which may have changed.
Member for
19 years 10 monthsHi KannanI need to correct my
Hi Kannan
I need to correct my previous answer.
If the contract form is a JCT Private with Approximate Quantities : 1986 then in accordance with clause 13 it states "The quality and quantity of the works included in the Tender Price shall be deemed to be that which is set out in the Contract Bills".
I have not researched later editions which may have changed.
Best regards
Mike Testro
Member for
17 years 4 monthsThanks Mike...
Thanks Mike...
Member for
19 years 10 monthsHi KannanYou are correct -
Hi Kannan
You are correct - the BoQ does not define the scope of works.
The Contractor must contruct and programme for the scope of works set down in the drawings and specification.
Best regards
Mike Testro