Variation in Re-measurable contract

Member for

19 years 10 months

Hi Kannan

I need to correct my previous answer.

If the contract form is a JCT Private with Approximate Quantities : 1986 then in accordance with clause 13 it states "The quality and quantity of the works included in the Tender Price shall be deemed to be that which is set out in the Contract Bills".

I have not researched later editions which may have changed.

Best regards

Mike Testro

Member for

17 years 4 months

Thanks Mike...

Member for

19 years 10 months

Hi Kannan

You are correct - the BoQ does not define the scope of works.

The Contractor must contruct and programme for the scope of works set down in the drawings and specification.

Best regards

Mike Testro