Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

difference between TIA and SIA

3 replies [Last post]
ISMAIL Abu Arra
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 18 Mar 2014
Posts: 3
Groups: None

hi, 

are Time Impact analysis and Schedule Impact Analysis refereing to the same or differnent concepts ?

 

thnaks 

Replies

Mike Testro
User offline. Last seen 35 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ismael

Not really - they are both the same techniques but according to the American's TIA is for work in progress and SIA is for completed projects.

Best regards

Mike Testro

ISMAIL Abu Arra
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 18 Mar 2014
Posts: 3
Groups: None

many thanks dear.

can we say that TIA is one of the approches of SIA ?

Mike Testro
User offline. Last seen 35 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ismail

These are American titles.

In the definitions section of types of analysis prepared for the Virginia Department of Transport:

http://www.virginiadot.org/business/resources/const/0703_PrinciplesofSIA.pdf

The terms are defined as follows:

Modification Impact Analysis (U.S. Army Corps of Engineers) – a contemporaneous

schedule impact analysis technique in which at the time of modification, the

actual status of the job is determined, the schedule is updated, and the delay is

inserted to quantify singular impact

Time Impact Analysis – similar to the Modification Impact Analysis, a schedule impact

analysis technique that recreates the actual status of the job at the time of

modification, updates the schedule, inserts delays, and quantifies singular impact;

although retrospective in that it is done after the fact, it has a contemporaneous

orientation, not a hindsight perspective

Schedule Impact – the potential effect of a delay or change on a project schedule; may

be in the form of delay or change in project completion date, delay or change in

project sequence, or consumption of float

Schedule Impact Analysis (SIA) – the process of quantifying and apportioning the

effect of delay or change on the project schedule.

 Which appears to mean that TIA is used for work in progress and SIA is forensic (or maybe not). Best regardsMike Testro