Dayaniddi is correct. The terms you need to look out for are "Lump sum" and "Re-measure".
A re-measure contract final account value is based on the quantity of works actually completed at the rates tendered. (Provided that the original BoQ was reasonably accurate in the anticipated quantities).
A lump sum contract final account value (in the absence of any variations) should be equal to the tender value. However if the contract is based on a BoQ provided by the Client and that BoQ is prooved to be inaccurate the Contractor is normally entitled to the recovery of the costs relating to errors/omissions contained in the BoQ.
Member for
22 years 7 months
Member for22 years7 months
Submitted by Dayanidhi Dhandapany on Wed, 2006-12-20 09:04
Contract sum or subcontract sum can be measurable or remeasurable? for an example, if you have 40,000m2 area of painting works, you can clearly let this package as subcontract(lumpsum). In case, if you want to let for an example excavation works, the subcontractor will go for unit rate basis, upto 3m rate1, next level rate2(more than the previous one)where you anticipate the estimated quantities may change in actual execution. in that case, during tender stage you can mention that the subcontract is of remeasurable type, but you can fix the unit rate depends on varying depths. during execution you can re-measure the quantities by some means(no of trucks etc.,)and pay the money.
Member for
18 years 9 monthsRE: The differences between Tender Sum & Sub Contract Sum
Dayaniddi is correct. The terms you need to look out for are "Lump sum" and "Re-measure".
A re-measure contract final account value is based on the quantity of works actually completed at the rates tendered. (Provided that the original BoQ was reasonably accurate in the anticipated quantities).
A lump sum contract final account value (in the absence of any variations) should be equal to the tender value. However if the contract is based on a BoQ provided by the Client and that BoQ is prooved to be inaccurate the Contractor is normally entitled to the recovery of the costs relating to errors/omissions contained in the BoQ.
Member for
22 years 7 monthsRE: The differences between Tender Sum & Sub Contract Sum
Contract sum or subcontract sum can be measurable or remeasurable? for an example, if you have 40,000m2 area of painting works, you can clearly let this package as subcontract(lumpsum). In case, if you want to let for an example excavation works, the subcontractor will go for unit rate basis, upto 3m rate1, next level rate2(more than the previous one)where you anticipate the estimated quantities may change in actual execution. in that case, during tender stage you can mention that the subcontract is of remeasurable type, but you can fix the unit rate depends on varying depths. during execution you can re-measure the quantities by some means(no of trucks etc.,)and pay the money.
Member for
19 years 5 monthsRE: The differences between Tender Sum & Sub Contract Sum
Hi,
I was told JCT dom1 explain this but I do not have a dom1.
Could someone else confirm?
Are there any good reference book that explain/guide on sub contract?