Time to Go Column & Hiding duration for the summary line

Hi,

How can I add the column to show the remaining days for an activity to start? I assume it should be a formula Today's date minus the activity's start date. Please see the photo below;

1.png

Also, how can I hide the start/finish/duration columns' values for the summary lines? Please see photo below;

11.png

Thank you very much in advance.

Kind regards,

Yarkin

Y
Yarkin Bilgic 👤 Member for 6 years 9 months

Thank you for your reply, I couldnt reflect the changes to the summary headings. Could you please show me steps if you dont mind? Also, for the time to go column, do you have any idea how to insert it?

Thank you,

Kind regards,

Yarkin

B
Ben Taunt 👤 Member for 14 years 5 months

Hi Yarkin,

It looks like your view has a sort on it.  If so, the setting to hide column details on a sort is within the Sort/Group Properties:

[[wysiwyg_imageupload:7468:]]

You will need to chose "Sub-heading with only name column" to get the desired view.

Thanks,

Ben @ Powerproject 

Forum Sponsor

Top Posters

Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts