Display link slope or the difference of two dates

Hi, 

I'm fairly new to planning softwares but I get the basics of powerproject. My problem is that I can't display a column which shows link slope. Is it even posisible? There is a link loop but I ignored the link between these two tasks and now it doesn't affect my schedule. The problem is I can't easily see how many days do I have to shorten the lag or duration of one task to make the schedule work.

I thought another solution, if it is not possible to display link slope, is to create a formula which subtracts the successors start date with predeccors start date and displays priority traffic light as green if the result is positive and red if the result is negative. 

I know it is difficult to understand a problem or try to solve it when you can't really see it yourself. However please feel free to ask and I try my best to give more details.

R
Rafael Davila 👤 Member for 22 years 3 months

Finding link loops:  A link loop is a logical error in a plan whereby a link or series of links results in a later task imposing a logical constraint on an earlier activity. 

Link loops caused by links with maximum lag:  In certain circumstances, specifying a maximum lag time on a link can cause a link loop that at first sight does not look like a link loop.

  • Are you modeling maximal lag?

It looks like you shall be looking for Relationship Free Float [RFF] or Slack:

You said you are fairly new to planning software but what you are looking for is not for the new to planning!

Forum Sponsor

Top Posters

Lee Mallek
23 posts
Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts