Is there a shortcut way of entering progress on ASTA?

Y
Yasine Ali 👤 Member for 10 years 10 months

Hello everyone, 

I was wondering if there was a shortcut way of entering progress into ASTA activities.

I know that you can select the little box on the bottom corner and also use the mouse to drag percentage on the actual bar.

However I was wondering if there was a way where you could just click the bar and then enter a number on the keyboard for a % of how much has been completed.

Y
Yasine Ali 👤 Member for 10 years 10 months

Hi Mike

Thank you for that

Just tried it

You have to use "paste values" instead of "paste" option

Works a treat thanks!

M
Mike Testro 👤 Member for 20 years 6 months

Hi Yasine - welcome to planning planet.

Yes my method is very quick

Set your progress percentages into a spreadsheet against each task.

Make sure that the tasks on the Asta view are lined up with the spreadsheet - I do this by filtering the tasks with no restraints so only the tasks show.

It is essential that they DO line up.

Set up the chart progress column to show percent complete - save this as a view called progress entry.

Make sure your progess period is set to the correct data date.

Now copy / paste all the spreadsheet percent numbers into the progress column and reschedule - job done in 3 minutes max - even with 10,000 tasks.

Give it a try.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts