Asta - Draw curve if vertical

Hello All,

 

Hope you all had a great and rested weekend. A programme has been set to draw curve if vertical by default so everytime i draw a link between 2 tasks, the link will become curve automatically if its vertical.

 

Can i know how do i reset it to straight link by default? 

P.S I can set the links to straight link manually after i drew a curved link but that would be a bit waste of time. I want a straight link by default.

 

Many thanks

Mike Planner

M
Mike Testro 👤 Member for 20 years 6 months

Hi Mike

This is in two stages.

First go to Tools > Default > Link and untick the draw curved box.

Second select a link and then Ctrl A to highlight every link

Right click any link and choose Properties and untick draw curved.

Best regards

Mike Testro

Forum Sponsor

Top Posters

AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts