Asta Power v11 - Progress line not transferring when imported in P6 v 6.2

While progress line on a programme generated with Asta Power Project (APP) with v11 is @ 10/08/12. When file is saved as Primavera .xer and either re-opened in APP on in P6 V6.2, progress line/data date is changed to 24/03/12 which is actually the start of the project? What I should I be checlking?

Additionally, when programme either re-opened in APP on in P6 V6.2, start of in-progress activities are actualised in 2008/2009 and end dates brought back in?

Any ideas.

M
Mike Testro 👤 Member for 20 years 6 months

Hi Emmanuelle

The transfer between Asta and P6 is never perfect and small adjustments sometimes have to be made - particularly with calendars.

So i suggest you reset the progress line in P6 to the required date and check for any other peculiarities.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts