Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Histogram To Count Tasks

2 replies [Last post]
Chris Lothian
User offline. Last seen 1 year 18 weeks ago. Offline
Joined: 18 May 2007
Posts: 34

Hi All,

I'm trying to create a histogram that counts the number of Tasks at the instant in time that have a been alllocated with a cost centre value, rather unsuccessfully at the moment.

Does anyone know how?

Thanks,

Chris.

Replies

Mike Testro
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Chris

Alternatively create a dummy cost item at £1.00.

Best regards

Mike Testro

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Create a Dummy Resource, make it to be a non-leveling resource and assign a unit of this resource to all activities then the histogram for this resource shall display what you are looking for.