Histogram To Count Tasks

Hi All,

I'm trying to create a histogram that counts the number of Tasks at the instant in time that have a been alllocated with a cost centre value, rather unsuccessfully at the moment.

Does anyone know how?

Thanks,

Chris.

M
Mike Testro 👤 Member for 20 years 6 months

Hi Chris

Alternatively create a dummy cost item at £1.00.

Best regards

Mike Testro

R
Rafael Davila 👤 Member for 22 years 4 months

Create a Dummy Resource, make it to be a non-leveling resource and assign a unit of this resource to all activities then the histogram for this resource shall display what you are looking for.