Scheduled Resource Reports

Hi All,

I am trying to set up a tabular report in excel so that others who cannot use Asta can view resource levels. I have used MS Project, and would very much like a table similar to that of either the Resource Sheet or Resource Usage views that are available as default in MS Project.

I need the resource name to be listed down the left column, with its daily/weekly/monthly or total assignment in a column to its right.

 

Thanks

 

Chris

M
Mike Testro 👤 Member for 20 years 6 months

Hi Chris

The easiest way is to set up the required columns in the left hand PowerProject spreadsheet and just copy /paste directly to excell.

Alternatively you can set up a resource Histogram view and export data directly to excell.

Finally within Asta Powerproject there is a powerful report writer that will export data directly to Excell - but that is a bit messy.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts