Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Change all "time" per Calendar

I am preparing the recovery program and we know that many activities are progressing already and the problem is the finish "TIME" is not the end time of the day. Say for example, Blockworks is at 30% and it gives me the finish date as 30 August 2019 10AM. Not to include the completed activities which have a 3PM or 2:30PM time. I want to change all of these to the end time, say 5PM per calendar. Is there a way to do this?

Market Place

No results found... (try selecting a different content filter)