Venetia Diamond mine

Planner, Murray & Roberts, Venetia Diamond mine

START Date: 
January, 1991
END Date: 
December, 1992

Site planner for Structural, Mechanical and Piping installation’s on a new process plant and open cast Diamond Mine called Venetia Mine. Fast track project with 27000 tons of structural steel and mechanical equipment. Project scheduling software was Prestge Project Planner and Open Plan. Was responsible for controls and progress measurement of steelwork erection. First introduction to use of bar-code technology through RS232 ports to handheld units to control measure of structural steel erection. Responsible for planning of all ranges of mechanical and plate work items installation.

Experience Hours (Planning & Scheduling): 
3950