Search

Resource histogram by weeks.

Forum Topic

I'm doing something wrong. I can't get my resource histogram to display by week. It sums to month. Help.[[wysiwyg_imageupload:2382:]]

Jan 30, 2015

Resource Finish Dates Differs on Activity finish Dates

Forum Topic

Dear Planners,I got encounter this kind of problem when I undergone a recovery plan to my project, of which after finalizing the schedule I exported the resources to get the resource planned based on the activity loading. I found out that the dates a...

Jan 31, 2015

Micro Progress changing month?

Forum Topic

Hello TILOS user Guru's,Am doing import of micro progress, everything working fine except month date on progress is being changed from December to January.Anyone experienced this? Have checked parameters and everything looks OK here, see below; Advic...

Feb 1, 2015

Data Migration & P6

Forum Topic

Does anybody know where P6 keeps your data files?   We have been informed that everyone in the business is getting a new computer over the next few months, and that existing data needs to be backed up and transferred over when the new machines arrive...

Feb 2, 2015

Late Curves in an Updated Schedule

Forum Topic

Need some help please!I have been asked to generate late curves in an updated schedule. I am able to make it, however i have some observations that I think P6 release 8.3.2 is generating it incorrect. My understanding is that there should be no remai...

Feb 3, 2015

Longest path forensics

Forum Topic

I have a schedule with 5 substantial comletion activities.  i am trying to sort a way to see the longest path of completed items to each substantial completion.  Does anyone know how to do this through P6?

Feb 3, 2015

Best Planning Software

Forum Topic

Hi thereIve recently moved to a new company and went from using P6 to MS Project, i havent had any training on MS Project and basically taught myself over the last 5 weeks. Trouble is its not a great resource utilisation tool - i may be wrong on this...

Feb 4, 2015

Critical Activity and Longest Path

Forum Topic

Dear Planners.What is the diffeerence between defining critical activities as:1- Total Float less than or equal to ....(e.g zero)2- Longest Path.Best,Moutaz

Feb 5, 2015

Setting up a Baseline in Microsoft Project 2013

Forum Topic

If you're unsure how the baseline feature works in Microsoft Project 2013, here's a step by step guide on how to set up a baseline in Microsoft Project http://ow.ly/IB8RZ

Feb 6, 2015

Event Error UPFE(-2175-2

Forum Topic

While attempting to set up the page or preview the print, i am getting the event error UPFE(-2175-2. If i print the file directly, then, it prints only the first page and shows printing on progress. And there after no result.  Can anyone provide a so...

Feb 7, 2015

Asta - Draw curve if vertical

Forum Topic

Hello All, Hope you all had a great and rested weekend. A programme has been set to draw curve if vertical by default so everytime i draw a link between 2 tasks, the link will become curve automatically if its vertical. Can i know how do i reset it t...

Feb 9, 2015

Time Is a Cost Even When Nobody Says How Much

Forum Topic

I just published a new blog post “Time Is a Cost Even When Nobody Says How Much” at the Total Project Control  website.  The new blog explains to that even when the sponsor/customer doesn’t recognize the value/cost of time and/or doesn’t know how to ...

Feb 9, 2015

Free Float

Forum Topic

Dear all, I want to indicate Free Float in MSP, both in a column and in the Gnatt bar, is it possible. Regards,satish

Feb 9, 2015