monthly engineering works tracking progress report

please i need urgent monthly engineering works(materials +long lead items +procurement+delivery) tracking progress report include weitage and percent complete

Z
Zoltan Palffy 👤 Member for 16 years 10 months

filter for materials +long lead items +procurement+delivery activities and determine the best way to weight them. Why do think that we have any idea what percent complete any of these would be ? Thats impossible