Carpentry Final Fixing
Task / DescriptionSlow Ave Fast Units Windows, Softwood, 3.0-7.0m20.6 0.4 0.3 hrs/no Windows, Softwood, 7.0-10.0m21.3 0.9 0.6 hrs/no Windows, Hardwood, 1.0-3.0m20.4 0.3 - hrs/no Windows, Hardwood, 3.0-7.0m20.7 0.5 0.4 hrs/no Windows, Hardwood, 7.0-10.0m21.6 1.2 0.7 hrs/no Windows, Aluminum, 1.0-3.0m20.2 0.3 - hrs/no Windows, Aluminum, 3.0-7.0m20.5 0.4 0.3 hrs/no Windows, Aluminum, 7.0-10.0m21.2 0.8 0.5 hrs/no Windows, Steel, 1.0-3.0m20.4 0.3 0.2 hrs/no Windows, Steel, 3.0-7.0m21.2 0.6 0.5 hrs/no Windows, Steel, 7.0-10.0m21.4 1.2 1.0 hrs/no Window Boards, nailed- 0.3 0.2 hrs/m Window Boards, screwed- 0.4 0.3 hrs/m Mouldings, Softwood, Nailed- 6.3 8.5 m/hr Mouldings, Softwood, Screwed- 4.6 5.6 m/hr Mouldings, Softwood, Gun Nailed- 8.2 11.1 m/hr Mouldings, Hardwood, Nailed- 3.3 5.5 m/hr Mouldings, Hardwood, Screwed- 2.4 3.7 m/hr Mouldings, Hardwood, Gun Nailed- 8.5 11.3 m/hr Skirting, Aluminum, Screwed 150-300mm centres- 7.6 - m/hr Skirting, Aluminum, Screwed 300-450mm centres- 4.5 - m/hr Skirting, Plastic, Adhesive Fixing- 8.6 - m/hr Architrave Mouldings9.5 12.2 18.2 m/hr Architrave, Fix to Doors- 1.2 - hrs/door Door Stop Mouldings10.1 16.9 25.0 m/hr Glazed Bead Mouldings15.5 18.6 20.4 m/hr Hanging Doors, Softwood, Single Pair Butts1.3 0.9 0.6 hrs/no Hanging Doors, Hardwood, Single Pair Butts1.9 1.2 0.9 hrs/no Cut Mortice to Receive Lock, Softwood- 0.2 - hrs/no Cut Mortice to Receive Lock, Hardwood- 0.6 - hrs/no Cut & Fix Formica Bath Panel- 0.4 - hrs/no Kitchen Cupboards, Floor Units- 0.8 0.6 hrs/no Kitchen Cupboards, Wall Units- 0.7 0.5 hrs/no Kitchen Cupboards, Shelf Units- 0.8 0.7 hrs/no Staircase, pre-made, simple, straight flight1.9 1.5 1.1 hrs/no Staircase, pre-made, 2 straight flights, 1 landing3.7 2.9 2.6 hrs/no Staircase, pre-made, 2 straight flights, 2 landings- 6.3 - hrs/no Staircase, Balustrades/Handrails, fix horizontal1.2 0.6 0.1 hrs/no Staircase, Balustrades/Handrails, fix raking0.9 0.5 0.3 hrs/no Staircase, Cut and Fix Newel to Walls0.9 - 0.2 hrs/no Windows, Softwood, 1.0-3.0m20.3 0.2 - hrs/no Raised Flooring, metal system- 0.5 - m2/hr
Book navigation for Carpentry Final Fixing
-
-
-
-
-
-
-
-
-
-
-
-
Carpentry Final Fixing
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-