Rule of Thumb

P
PP Admin 👤 Member for 17 years 4 months

Rule of Thumb

Task / DescriptionSlow  Ave  Fast   Units Site Investigation Pre Drilling5.0 4.0 3.0  days/no Ground Excavation, Hydraulic Backhoe-  50.0 -   m3/day Bored Piling, 25-70m deep10.0 8.0 6.0  days/no Formwork Fixing-  12.0 -   m2/day Reinforcement Fixing-  0.7 -   Tonnes/day Concrete Placement-  16.0 -   m3/day Scaffold Erection, Steel Falsework-  140.0 -   m3/day Blockwork Laying-  7.0 -   m2/day Plastering and Rendering-  12.0 -   m2/day Blockwork Laying7.0 12.0 17.5  m2/day Stonework Cladding-  5.1 -   m2/day Window Glazing-  1.5 -   m2/hr Granolithic Flooring-  4.5 -   m2/hr Floor Screeding-  4.5 -   m2/hr Floor Screeding-  60.0 -   m2/day Ceramic Wall Tiling-  1.5 -   m2/hr