Carpentry & Joinery

Carpentry & Joinery

Task / DescriptionSlow  Ave  Fast   Units Formwork to Soffit of Manhole-  1.8 -   m2/hr Formwork to Walls of Manhole11.2 14.2 20.2  m2/hr Formwork to Road Edges, straight-  7.7 -   m/hr Formwork to Road Edges, curves-  6.2 -   m/hr