Partitioning

P
PP Admin 👤 Member for 17 years 4 months

Partitioning

Task / DescriptionSlow  Ave  Fast   Units Timber Studding5.9 6.2 6.8  m/hr Metalwork System (MF) Studding1.6 2.0 2.5  m2/hr Tape, Joint Sand and Top Coat Plasterboard1.1 1.5 2.1  m2/hr Skimming to Plasterboards5.5 6.1 6.7  m2/hr 5mm Hardboard Paneling, excluding studding time-  3.2 3.6  m2/hr 100mm Pine Paneling, excluding studding time0.8 1.1 1.4  m2/hr Quality Hardwood Paneling, excluding studding time0.3 0.5 0.6  m2/hr Fix 50mm Rocksil Insulation to cavities-  17.8 20.2  m2/hr Fix Timber Studding and Paramount Partitions2.6 3.0 3.4  m2/hr Fix Timber Studding and Demountable Partitions0.8 1.1 1.6  m2/hr Fix Timber Studding and Hills Duraboard Partitions3.0 3.5 3.9  m2/hr Fix Timber Studding and Gyproc Laminated Partitions2.2 2.6 2.9  m2/hr Stud Partitions, Butt Jointed, nailed5.9 7.3 9.1  m/hr Stud Partitions, Butt Jointed, screwed3.5 4.6 5.8  m/hr Stud Partitions, T&G Jointed, nailed2.9 3.6 4.8  m/hr Stud Partitions, T&G Jointed, screwed2.1 2.8 3.7  m/hr Stud Partitions, Fix Sole Plates-  11.1 -   m/hr Stud Partitions, Fix Noggins-  16.6 -   m/hr Stud Partitions, Drill 25-40mm Holes-  28.5 -   no/hr Fix Toilet Partition System, Separation panels-  0.8 -   hrs/no Fix Toilet Partition System, Wall Front Panels-  0.7 -   hrs/no Fix Toilet Partition System, Separation Front Panels-  0.6 -   hrs/no Fix Toilet Partition System, End Front Panels-  0.6 -   hrs/no Fix Toilet Partition System, Hang Door to Panel-  0.4 -   hrs/no Fix Toilet Partition System, Hand Door plugged to wall-  0.6 -   hrs/no Fix Toilet Partition System, Fix Head Rails-  0.1 -   hrs/no