Footing formwork

P
PP Admin 👤 Member for 17 years 4 months

Activity

TASKS

Task - UOM

Labor (L) - Carpenter (Mandays)

Labor (L) - Helper (Mandays)

Material (M)

Material (M)

Material (M)

Footing formwork

Footing - Shuttering & Providing Support

Sqm

0.8 Mandays/10Sqm

1.5 Mandays/10Sqm

MS Wall Form Panel - 1250 x 500 : 16Nos/10Sqm

Props - 2m to 3m Long : 2 Nos/Rm

Shuttering Oil : 4Ltr/10Sqm

 

Footing - Deshuttering & insitu Stacking

Sqm

0.48 Mandays/10Sqm

0.9 Mandays/10Sqm