Longest path forensics

I have a schedule with 5 substantial comletion activities.  i am trying to sort a way to see the longest path of completed items to each substantial completion.  Does anyone know how to do this through P6?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

the easy way is if all of the 5 substantial completion milestones have different float values. Then you can just filter for that float value. 

The hard way is to filter for just one substantial completion milestones and then go to the precedessor window and loook for the predecessor that has is both the driving and critical boxes checked and then click on that predecessor and then click on the GOTO button for that predecessor keep doing this until you get back to the data date. 

If you want to to you can add a code for this substantial for this completion milestone and assign all of the activities to this code for that lead up to this substantial completion milestone.

you can use the same technique for the other 4 substantial completion milestones and create codes for them also 

so now if you want to see all 5 paths just filter for the 5 new codes that you just made.

please keep in mind as soon and you progress this schedule and ot make and changes to the schedule you wil have to repeat this process again becasue the paths could have changed. 

 

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts